The ground floor of a mixed-use building is where the electrical design gets complicated. The apartments above are repetitive and predictable. The retail below is a blank shell that will be leased to a tenant nobody has met yet, who may turn out to be a nail salon, a restaurant with a 200-amp kitchen, or a bank branch with a server room. The decisions a developer makes about that space during base-building construction decide how painful every future lease will be.
Having built both the base buildings and the fit-outs inside them for brands like Starbucks, Restoration Hardware and Buffalo Wild Wings, here is what we would settle before the shell is finished and before the lease is signed.
Decide the retail power allowance early, and make it generous
Base building
The cheapest time to give a retail bay power is while the switchgear is being ordered. A common mistake is sizing each retail space at the minimum the code requires for a generic mercantile occupancy, then discovering that the only tenant who wants the corner is a restaurant. Restaurants, medical and fitness tenants routinely need two to four times the power of a boutique. Bringing a second feeder to a bay after the ceiling above is finished and the apartments are occupied costs many times what it costs during construction.
Our rule of thumb for developers: size the retail distribution for the heaviest tenant you would accept at each bay, not the lightest, and put the spare capacity in the gear even if the feeders are run later. Give every bay its own meter, its own disconnect and a conduit pathway back to the electrical room with room to pull more.
Write the lease around a clear line: landlord’s work vs. tenant’s work
Most disputes we see on retail fit-outs trace back to a lease exhibit that was vague about where the landlord’s electrical stops. The clean version reads something like this: the landlord delivers a metered service of a stated size, terminated at a disconnect or panel at a stated location inside the premises, with a stated number of empty conduits to the roof and to the electrical room. Everything from that point in is tenant’s work. Any upgrade to the landlord’s service to meet tenant load is tenant’s cost, at landlord’s option through landlord’s contractor.
Spell out the size in amps and voltage, not in words like “adequate.” Put the location on a drawing. If the tenant’s signage, HVAC or kitchen exhaust will need power on the roof, say who runs it and who maintains it.
Coordinate the systems that cross the line
Some systems cannot be split neatly between landlord and tenant, and those need an owner from day one.
- Fire alarm. The retail space is part of the building’s fire alarm system, so tenant devices have to tie into the base-building panel, be programmed by whoever maintains that panel, and be tested together. Decide whether tenant fire alarm work must go through the landlord’s fire alarm contractor; on most buildings it should.
- Kitchen hood suppression and exhaust interlocks. A restaurant’s suppression system has to shut down gas and power under the hood and signal the building alarm. That is a three-way coordination between the tenant’s kitchen contractor, the fire alarm contractor and the electrician.
- Signage and exterior lighting. Storefront signs, canopy lighting and blade signs usually run on the house meter or the tenant meter depending on who controls them. Pick one, and provide the circuit during base building.
- Emergency and egress lighting. Shared corridors, rear exits and the path through the retail to the street are life-safety items the inspector will test as part of the building, not the tenant.
Plan the shutdowns, because you will have residents upstairs
By the time the first retail tenant builds out, the apartments are often occupied. Any work in the main electrical room, any new feeder from the switchgear and any fire alarm programming can affect the people living above. A good fit-out contractor schedules those events, notifies the property manager, and works nights where a shutdown is unavoidable. A lease that requires the tenant’s contractor to coordinate shutdowns through the landlord, with notice, saves everyone a bad week.
Inspections and the certificate of occupancy
A retail fit-out gets its own electrical permit and its own inspections, but the certificate of occupancy for the tenant space depends on the base-building systems being in order, especially fire alarm. If the base building has open items, the tenant’s opening date is at risk, and that becomes a landlord problem fast. We recommend closing out the base-building electrical fully, with the fire alarm acceptance test complete, before the first tenant starts work.
A short checklist for developers
- Size retail distribution for the heaviest acceptable tenant per bay, with spare capacity in the gear.
- Separate meter, disconnect and spare conduits for every bay.
- Lease exhibit states service size, termination point and the landlord/tenant line on a drawing.
- Tenant fire alarm work routed through the building’s fire alarm contractor.
- Roof power for signage, HVAC and exhaust provided during base building.
- Shutdown procedure written into the lease.
- Base-building electrical and fire alarm closed out before the first tenant mobilizes.
Sunderland Electric builds the base-building electrical for mixed-use projects across Connecticut and the retail fit-outs that follow, which is why we care about getting the handoff between them right. If you are planning a mixed-use project, send us the drawings and we will flag the retail power questions before they cost anything.