A restaurant is the most electrically demanding tenant a mixed-use or retail building will ever have, and the fit-out is where that shows up. A 3,000 square foot office suite might need a 100 amp panel. A 3,000 square foot restaurant with an electric kitchen can need 400 amps or more, three-phase, plus a hood fire-suppression interlock, a walk-in cooler on its own circuit and a dozen dedicated receptacles the equipment schedule did not mention. Here is what we look for when we price and build a restaurant fit-out in Connecticut.
1. Start with the kitchen equipment schedule, not the drawings
The electrical drawings are only as good as the equipment list they were drawn from, and the equipment list changes between design and construction more often than not. Before we rough in, we want the final kitchen equipment schedule with the nameplate volts, amps and phase for every piece: ovens, fryers, flat-tops, dish machines, booster heaters, refrigeration, ice machines and espresso equipment. An electric combi oven alone can draw 60 amps at 208 volt three-phase. If the operator switches from gas to electric cooking lines mid-stream, the feeder and the panel both change.
2. Service capacity and who pays for it
In a mixed-use building the restaurant usually gets a dedicated meter and a feeder from the house switchgear. The question is whether the landlord’s base building left enough capacity for it. We have seen plenty of ground-floor retail bays roughed in at 200 amps single-phase on the assumption that a boutique would move in, and then a restaurant signs the lease. Adding three-phase 400 amp service to a bay after the building is occupied can mean new feeders through a finished ceiling and a utility upgrade. The lease should say what the landlord delivers; our post on retail fit-out electrical in mixed-use buildings covers how to write that scope.
3. The hood: fire suppression, exhaust and make-up air
The commercial kitchen hood is where the electrical, mechanical and fire-protection trades meet, and it is where fit-outs most often fail inspection. The hood’s fire-suppression system must shut down power to the cooking equipment under the hood when it discharges, which means a shunt-trip breaker or contactor on every circuit feeding that equipment, wired to the suppression system’s micro-switch. The exhaust fan and the make-up air unit are typically interlocked so one cannot run without the other, and both must start when the suppression system trips. The gas valve, if there is one, closes on the same signal. Get the hood manufacturer’s wiring diagram early and coordinate it with the mechanical contractor before the ceiling closes.
4. Dedicated circuits and the receptacles nobody drew
Nearly every piece of kitchen equipment wants its own circuit, and many want a specific receptacle configuration. Refrigeration, ice machines, dish machines and anything with a motor should never share. The front of house has its own list: point-of-sale terminals, printers, music, TVs, a bar with blenders and glass washers, and outdoor seating that needs weatherproof GFCI receptacles. Walk the space with the operator’s equipment list in hand and count receptacles by location. The number is always higher than the drawings show.
5. Lighting, controls and the energy code
Restaurant lighting is part of the brand, and the designer’s fixture package is usually decorative and dimmed. Connecticut’s energy code still applies: lighting power limits, automatic shut-off, and daylight controls where there is enough glass. We make sure the dimming system, the decorative fixtures and the kitchen’s bright task lighting all work with the required controls, and that the emergency lighting and exit signs are on the base building’s emergency circuit or their own battery backup. Our Sally’s Apizza South Norwalk project is a good example of decorative dining-room and bar lighting built to the current code.
6. Low voltage and the opening-day list
Data drops for the point-of-sale system, kitchen display screens, Wi-Fi, security cameras, the sound system and the walk-in temperature alarm all need rough-in before the walls close. Restaurants also need a working fire alarm connection to the base building system and, where required, a health-department inspection that checks lighting levels over prep areas. Build the opening-day inspection sequence into the schedule: fire marshal, building official, health department, then the operator’s soft opening.
Sunderland Electric builds restaurant and retail fit-outs for landlords, operators and general contractors across Connecticut, including tenant spaces in the mixed-use buildings we wire from the ground up. Send us the equipment schedule and the drawings and we will price the fit-out with the hood and kitchen loads broken out.