Category: Insights

Electrical planning insights for Connecticut developers, general contractors and building owners.

  • Generator Sizing for Mixed-Use Buildings: Elevators, Fire Pumps and Life-Safety Loads

    Generator Sizing for Mixed-Use Buildings: Elevators, Fire Pumps and Life-Safety Loads

    Generator sizing on a mixed-use building is not an adding-up exercise. It is a question of which loads must start together, which ones are motors, and what happens to the voltage when a fire pump and an elevator both try to start a second after the utility drops. Get that right and the generator is often smaller than the first estimate. Get it wrong and the lights dim every time the elevator leaves the lobby.

    1. Build the load list by category first

    Before any kilowatt number, sort the loads the way the code does: emergency (egress lighting, exit signs, fire alarm), legally required standby (fire pump, smoke control, firefighter elevator) and optional standby (everything the owner wants to keep running). We explained the categories in emergency vs. standby generators for apartment buildings. The generator has to carry the first two categories under all conditions. The third is a business decision, and it is where most of the size comes from.

    2. Running load versus starting load

    Lighting and electronics draw what their nameplate says. Motors do not. A motor can draw six times its running current for the second or two it takes to come up to speed, and a generator that can carry the running load comfortably may stall or drop voltage badly when a large motor starts. Fire pumps, elevator machines, booster pumps, HVAC compressors and large exhaust fans are all motors. The generator has to be sized for the largest motor-starting event on top of whatever is already running, which is why the sequence of operations matters as much as the total.

    3. Fire pumps are the special case

    If the building has an electric fire pump on the generator, that pump drives the sizing. The code requires the generator to start the fire pump at locked-rotor current without the voltage sagging more than the fire pump controller allows, and it generally has to do so with the other required loads already connected. A 50 horsepower fire pump can push a generator from the 150 kW range into the 300 kW range on its own. A reduced-voltage or soft-start fire pump controller eases this, but the engineer has to design for it, and the generator manufacturer’s sizing software has to be run with the fire pump’s actual starting characteristics, not a generic estimate.

    4. Elevators, and the trick of staggering

    Elevators on standby power are usually brought back one car at a time by the elevator controller, which is a form of load staggering built into the equipment. Transfer switches can do the same for other loads: the emergency transfer switch closes first, the legally required loads a few seconds later, the optional loads last. Staggering means the generator never sees all the starting currents at once, and a generator with a modest running capacity can handle a surprisingly large connected load. Regenerative elevator drives add a wrinkle: when a loaded car descends it pushes power back onto the bus, and a generator cannot absorb it. The elevator contractor’s spec should address this, typically with a braking resistor.

    5. Mixed-use adds the tenant question

    In a mixed-use building the residential side and the commercial side often want different things from the generator. The residential side needs corridors, stairs, elevators and sometimes heat. A restaurant tenant may want its walk-in coolers backed up to protect inventory; a medical or pharmacy tenant may need more. Decide early whether tenant optional loads are on the house generator at all. If they are, each tenant feed needs its own metering and transfer arrangement so the landlord can recover the cost, and the generator grows accordingly. If they are not, say so in the lease and let the tenant provide its own.

    6. The numbers to hand the engineer

    The generator manufacturer’s sizing tool needs: every load by category with its running kW, every motor with horsepower and starting method, the order in which the transfer switches close, the allowable voltage dip, the fuel type and the required run time. With those, the engineer lands on a size with margin for growth, and the contractor can price the generator, the transfer switches, the fuel and the pad or roof structure accurately. Without them, every bidder guesses, and the guesses do not match.

    Sunderland Electric installs generators, transfer switches and service and distribution for mixed-use and multifamily buildings across Connecticut. Send us the load schedule and we will price the backup power system with the motor-starting assumptions spelled out.

  • Fire Alarm Systems for Multifamily Buildings: Addressable vs. Conventional, and When Each Fits

    Fire Alarm Systems for Multifamily Buildings: Addressable vs. Conventional, and When Each Fits

    The fire alarm system is the one part of an apartment building the fire marshal signs off on personally, and it is the system most likely to delay a certificate of occupancy if it is designed late or built out of sequence. The first design decision is whether the system is conventional or addressable, and on anything bigger than a small walk-up the answer is now almost always addressable. Here is why, and what else a developer should settle early.

    1. Conventional versus addressable, in plain terms

    A conventional system wires devices in zones. When a smoke detector trips, the panel reports the zone, such as “third floor east,” and someone has to walk the zone to find the device. An addressable system gives every device its own identity on a signaling loop. The panel reports “smoke detector, Unit 312, bedroom corridor,” and it can also tell you that the detector in 207 is dirty before it causes a false alarm. Addressable panels cost more, but they use less wire, support far more devices per loop, and make the inspection, testing and troubleshooting that follow for the next 20 years dramatically cheaper.

    2. When conventional still fits

    A small building, say a dozen units over two or three floors with a single stair, can be served well by a conventional panel with a handful of zones. The device count is low, the building is easy to walk, and the cost difference is real at that scale. Once a building has 30 or 40 units, multiple floors and a garage, the addressable system pays for itself in the first year of maintenance. For anything with an elevator, a sprinkler system with multiple flow switches, or a voice evacuation requirement, addressable is effectively the only practical choice.

    3. What goes in the units and what goes in the corridors

    Inside each apartment, the smoke alarms that wake sleeping residents are typically 120 volt interconnected alarms with battery backup, wired by the unit electrician and not part of the building fire alarm system. The building system covers the common areas: smoke detectors in corridors and at the top of stairs, heat detectors in mechanical rooms and garages, pull stations at exits, horn-strobes or speaker-strobes throughout, duct detectors in air handlers, and monitoring of the sprinkler flow and tamper switches. In many designs a detector or a sounder base in each unit is also tied to the building system so the building can alert the unit. The engineer’s drawings and the local fire marshal decide the exact mix; building it exactly as drawn is what gets it approved.

    4. The sequence that keeps the CO on schedule

    Fire alarm work touches every other trade, and the sequencing is where projects lose time. The panel location, the loop routing and the device locations need to be fixed before the corridor ceilings close. Duct detectors go in when the air handlers are set, not after. Sprinkler flow and tamper switches have to be wired before the sprinkler contractor tests the system. Elevator recall, which sends cars to a safe floor when a detector near the elevator trips, needs the elevator contractor on site for the acceptance test. And the whole system must pass a 100 percent device test witnessed by the fire marshal, which means the fire alarm contractor needs every device installed, labeled and programmed with a complete device list before that appointment. We cover the rest of the inspection in what inspectors check before the certificate of occupancy.

    5. Monitoring, power and the owner’s ongoing obligations

    The panel reports to a central station over a cellular or IP communicator, which the owner contracts for and pays monthly. The panel needs a dedicated circuit and a battery set sized for the required standby time. After opening, the system must be inspected and tested on the schedule the fire code requires, typically annually with some devices more often, and the records kept on site. An addressable panel makes that annual test a half-day job instead of a two-day job, which is the quiet reason most property managers prefer it.

    Decide it early

    Pick the panel manufacturer and system type during design, get the fire marshal’s review done before rough-in, and hold the fire alarm contractor to a device-by-device completion list. Those three things take fire alarm off the critical path.

    Sunderland Electric installs addressable fire alarm, emergency lighting and other life-safety systems on apartment and mixed-use buildings across Connecticut. Send us the drawings and we will price the life-safety scope alongside the rest of the electrical.

  • Load Sharing for Multi-Unit EV Charging: Adding Chargers Without a Service Upgrade

    Load Sharing for Multi-Unit EV Charging: Adding Chargers Without a Service Upgrade

    The math that stops most apartment EV projects is simple. Twenty Level 2 chargers at 40 amps each is 800 amps of connected load. On a building with a 1,600 amp service that is already carrying heat pumps, elevators and 150 units of cooking and laundry, there is no room for it, and the utility quotes a service upgrade that costs more than the chargers. Load sharing, also called load management or power sharing, is how the project gets built anyway.

    1. Connected load versus actual load

    Twenty chargers are almost never all drawing full power at the same time. Residents arrive home over several hours, most cars need only a partial charge, and a battery that is nearly full draws a fraction of the charger’s rating. Measured data from multifamily installations consistently shows peak demand well below half of the connected load, and often far less. The electrical code historically required the installation to be sized for every charger at full output anyway, which is what made the number so large. Load management changes that.

    2. How load sharing works

    A load-sharing system puts a group of chargers behind a controller that knows the total current the group is allowed to draw. The controller tells each charger how much it may deliver and adjusts continuously. If two cars are plugged in, each gets the full 40 amps. If twelve cars are plugged in on a 200 amp feeder, each gets about 16 amps, and as cars finish charging the remaining ones speed back up. Because every car is parked overnight, the slower rate rarely matters to the resident; the car is full by morning either way.

    The NEC recognizes this. An energy management system that limits the total EV load lets the installation be sized to the controlled maximum rather than the sum of the charger nameplates. A 200 amp feeder can legitimately serve a bank of chargers whose nameplates add to 800 amps, provided the controller is listed for the purpose and set so the group can never exceed 200 amps.

    3. Three ways to set the limit

    The simplest version is a fixed cap: the charger group is allowed a set number of amps and shares it. That works when the building has a known amount of spare capacity. The second version is dynamic: a current transformer on the building’s main feed tells the controller how much the rest of the building is using, and the chargers are allowed whatever is left. At 2 a.m. when the building is quiet the chargers run flat out; at 6 p.m. they throttle back. Dynamic management squeezes the most chargers onto a tight service. The third version adds utility signals, letting the building reduce charging during utility peak events in exchange for an incentive.

    4. What it costs and what it saves

    Networked chargers with built-in load management cost more per unit than basic chargers, and most carry a monthly network fee. Against that, the project avoids a service upgrade that can run from tens of thousands of dollars to well into six figures once a utility transformer and switchgear are involved, and avoids months of utility lead time. On almost every apartment building we have priced, load sharing is the difference between a project that happens and one that does not. The chargers also handle billing, so residents pay for the power they use. Our post on EV chargers with built-in load management covers the equipment side in more detail.

    5. Planning for growth

    The right design installs a dedicated EV panel and feeder sized for the eventual number of ports, runs conduit to every space that may get a charger, and installs chargers on a fraction of them at opening. Adding a charger later is then a matter of pulling wire and mounting a unit, not opening a slab. The controller’s cap is raised as the building’s actual load data justifies it. For a new building, this is a small line in the budget; for an existing building it is a planning exercise we can walk through with a look at the switchgear and a year of utility bills.

    Sunderland Electric designs and installs load-managed EV charging for apartment buildings, garages and mixed-use properties in Connecticut. Tell us how many spaces you want to serve and we will tell you what the existing service can carry.

  • Restaurant Tenant Fit-Out Electrical: Kitchen Loads, Hood Controls and Dedicated Circuits

    Restaurant Tenant Fit-Out Electrical: Kitchen Loads, Hood Controls and Dedicated Circuits

    A restaurant is the most electrically demanding tenant a mixed-use or retail building will ever have, and the fit-out is where that shows up. A 3,000 square foot office suite might need a 100 amp panel. A 3,000 square foot restaurant with an electric kitchen can need 400 amps or more, three-phase, plus a hood fire-suppression interlock, a walk-in cooler on its own circuit and a dozen dedicated receptacles the equipment schedule did not mention. Here is what we look for when we price and build a restaurant fit-out in Connecticut.

    1. Start with the kitchen equipment schedule, not the drawings

    The electrical drawings are only as good as the equipment list they were drawn from, and the equipment list changes between design and construction more often than not. Before we rough in, we want the final kitchen equipment schedule with the nameplate volts, amps and phase for every piece: ovens, fryers, flat-tops, dish machines, booster heaters, refrigeration, ice machines and espresso equipment. An electric combi oven alone can draw 60 amps at 208 volt three-phase. If the operator switches from gas to electric cooking lines mid-stream, the feeder and the panel both change.

    2. Service capacity and who pays for it

    In a mixed-use building the restaurant usually gets a dedicated meter and a feeder from the house switchgear. The question is whether the landlord’s base building left enough capacity for it. We have seen plenty of ground-floor retail bays roughed in at 200 amps single-phase on the assumption that a boutique would move in, and then a restaurant signs the lease. Adding three-phase 400 amp service to a bay after the building is occupied can mean new feeders through a finished ceiling and a utility upgrade. The lease should say what the landlord delivers; our post on retail fit-out electrical in mixed-use buildings covers how to write that scope.

    3. The hood: fire suppression, exhaust and make-up air

    The commercial kitchen hood is where the electrical, mechanical and fire-protection trades meet, and it is where fit-outs most often fail inspection. The hood’s fire-suppression system must shut down power to the cooking equipment under the hood when it discharges, which means a shunt-trip breaker or contactor on every circuit feeding that equipment, wired to the suppression system’s micro-switch. The exhaust fan and the make-up air unit are typically interlocked so one cannot run without the other, and both must start when the suppression system trips. The gas valve, if there is one, closes on the same signal. Get the hood manufacturer’s wiring diagram early and coordinate it with the mechanical contractor before the ceiling closes.

    4. Dedicated circuits and the receptacles nobody drew

    Nearly every piece of kitchen equipment wants its own circuit, and many want a specific receptacle configuration. Refrigeration, ice machines, dish machines and anything with a motor should never share. The front of house has its own list: point-of-sale terminals, printers, music, TVs, a bar with blenders and glass washers, and outdoor seating that needs weatherproof GFCI receptacles. Walk the space with the operator’s equipment list in hand and count receptacles by location. The number is always higher than the drawings show.

    5. Lighting, controls and the energy code

    Restaurant lighting is part of the brand, and the designer’s fixture package is usually decorative and dimmed. Connecticut’s energy code still applies: lighting power limits, automatic shut-off, and daylight controls where there is enough glass. We make sure the dimming system, the decorative fixtures and the kitchen’s bright task lighting all work with the required controls, and that the emergency lighting and exit signs are on the base building’s emergency circuit or their own battery backup. Our Sally’s Apizza South Norwalk project is a good example of decorative dining-room and bar lighting built to the current code.

    6. Low voltage and the opening-day list

    Data drops for the point-of-sale system, kitchen display screens, Wi-Fi, security cameras, the sound system and the walk-in temperature alarm all need rough-in before the walls close. Restaurants also need a working fire alarm connection to the base building system and, where required, a health-department inspection that checks lighting levels over prep areas. Build the opening-day inspection sequence into the schedule: fire marshal, building official, health department, then the operator’s soft opening.

    Sunderland Electric builds restaurant and retail fit-outs for landlords, operators and general contractors across Connecticut, including tenant spaces in the mixed-use buildings we wire from the ground up. Send us the equipment schedule and the drawings and we will price the fit-out with the hood and kitchen loads broken out.

  • Emergency vs. Standby Generators for Apartment Buildings: What Code Requires and What Owners Choose

    Emergency vs. Standby Generators for Apartment Buildings: What Code Requires and What Owners Choose

    “Do we need a generator?” is one of the first questions on a multifamily project, and the honest answer is that the building code decides part of it and the owner decides the rest. The two parts have very different costs, and mixing them up is how projects end up with a generator that is either too small for what the code requires or far larger than the business plan ever needed.

    1. Three categories, not one

    The National Electrical Code, which Connecticut adopts through the State Building Code, sorts backup power into three categories. Emergency systems (NEC Article 700) are the loads that keep people alive and let them get out: egress lighting, exit signs and fire alarm. Legally required standby systems (Article 701) are loads the code or the fire marshal requires but which are not immediately life-threatening if they fail, such as a fire pump or smoke control in a high-rise. Optional standby (Article 702) is everything the owner simply wants to keep running: elevators for convenience, the leasing office, a resident lounge, heat in the lobby.

    Each category has its own rules for how quickly power must be restored, how the wiring is separated from the normal building wiring, and how the system is tested and maintained. Emergency loads are the strictest; optional standby is the most flexible.

    2. What a typical Connecticut apartment building must have

    For a mid-rise wood-frame or podium building of four to six stories, the required emergency loads are small: egress and stair lighting, exit signs, the fire alarm panel and sometimes emergency communication. Those loads are often a few kilowatts in total, and the code allows them to be served by battery backup, either individual battery units in the fixtures or a central inverter, instead of a generator. Many Connecticut apartment buildings have no generator at all for this reason, and that is fully code-compliant.

    The picture changes once the building is tall enough to be a high-rise, has a fire pump, or has an elevator that must operate during a fire for firefighter access or accessible egress. At that point the code calls for a standby power source that can carry those loads for a defined period, and a generator becomes the practical answer. The engineer of record determines which loads fall into which category; our job is to build the system so the categories stay separate and the transfer equipment performs as designed.

    3. What owners choose to add, and why

    Once a generator is on site, the marginal cost of adding optional standby loads is mostly the size of the generator and a second transfer switch. Owners commonly add elevators (so residents are not stranded on upper floors during a storm), domestic water booster pumps, the building’s heating plant, the leasing office and a resident amenity space. In a building marketed to older residents or with a large share of work-from-home tenants, a generator that keeps elevators and corridors running during the next multi-day outage is a leasing advantage that can be worth more than its cost.

    What owners generally should not do is try to put the whole building on standby. Backing up every apartment means a generator sized to the full service, a very large fuel supply and an electric bill that reflects it. A targeted optional standby scope is the sweet spot.

    4. Fuel, location and the things that get missed

    Natural gas generators are the default on most of our projects because they avoid the fuel-storage and refueling issues of diesel, though diesel is still specified where the code requires on-site fuel for a set number of hours. The generator location drives a surprising amount of cost: a rooftop unit needs a crane and structural review, a grade-level pad needs clearances from windows, doors and air intakes, and either one needs a sound and exhaust plan the neighbors will accept. Run the generator pad and the transfer-switch room through the design early, not after the building footprint is fixed.

    The other common miss is the transfer switch count. Emergency loads need their own transfer switch; optional loads cannot share it. We wrote about keeping that equipment tested in why a backup generator needs a transfer switch.

    5. Getting the scope right in the bid

    When a bid package says only “generator, 150 kW” without a load schedule and a list of what sits behind each transfer switch, every bidder prices a different system. Ask the engineer for the emergency, legally required and optional load lists, the required run time, the fuel type and the location. With those five items, an electrical contractor can price the system accurately and tell you what adding or removing an optional load would do to the number. Our electrical bid package checklist covers what else belongs in that package.

    Sunderland Electric installs generators, transfer switches and life-safety power systems on apartment and mixed-use buildings across Connecticut. Send us the drawings and we will price the backup power scope with the load categories broken out.

  • Level 2 vs. DC Fast Charging for Apartment Buildings: Which Makes Sense for a Connecticut Property?

    Level 2 vs. DC Fast Charging for Apartment Buildings: Which Makes Sense for a Connecticut Property?

    Every apartment building we price in Connecticut now has EV charging somewhere in the scope, and the first question from the owner or developer is usually the same one: should we put in fast chargers? The short answer is almost never, and the reason has nothing to do with the chargers themselves. It has to do with how people charge at home, and what each type of charger asks of the building’s electrical service.

    1. What the two charger types actually are

    Level 2 charging is 208 or 240 volt AC. A typical commercial Level 2 charger draws 32 to 48 amps and adds 20 to 35 miles of range per hour. The car’s own onboard charger converts AC to DC, which is why the equipment on the wall is relatively simple and relatively inexpensive.

    DC fast charging bypasses the car’s onboard charger and delivers DC directly to the battery. Units run from 50 kW to 350 kW, and a mid-range 150 kW unit needs a 480 volt, three-phase feed at roughly 200 amps. One fast charger can draw as much power as 10 to 15 Level 2 ports running at once. It charges a car in 20 to 40 minutes instead of overnight.

    2. How tenants charge at home

    A resident with an EV plugs in when they get home and unplugs in the morning. That is eight to twelve hours of dwell time, and a Level 2 port fills any battery on the market in that window. Fast charging solves a problem apartment residents do not have: needing a full charge in half an hour. It is the right tool for a highway rest stop, a fleet depot or a retail site where drivers stay for an hour and leave. At an apartment building, a fast charger sits idle most of the day and competes with the building’s own peak load in the evening.

    3. What each does to the electrical service

    This is where the decision gets made. A 150-unit building might have a 2,000 or 2,500 amp service at 208Y/120 volts. Ten Level 2 ports with load management, as we describe in EV-ready apartment parking, can usually be carried on the existing service with a dedicated panel and some headroom planning. A single 150 kW fast charger needs its own 480 volt service or a step-up transformer, a separate utility application and, in many cases, a new pad-mounted transformer from the utility. The fast charger’s demand charges on the electric bill can also exceed its revenue unless it is heavily used.

    Put differently: the cost of one fast charger, including the service work, is usually more than the cost of 20 Level 2 ports, and it serves fewer residents.

    4. When DC fast charging does make sense

    There are three situations where we would recommend it on a multifamily or mixed-use property. First, a mixed-use building with ground-floor retail where the parking is public and short-stay; the fast charger serves the retail customers, not the residents. Second, a large campus or garage where a fast charger is a shared amenity for residents without assigned parking, backed by a bank of Level 2 ports for everyone else. Third, a site where the utility is already bringing in 480 volt service for other reasons, such as a central plant or large elevators, and the incremental cost is modest.

    5. Planning the Level 2 layout

    For most Connecticut apartment buildings the right plan is a Level 2 installation sized for today’s demand with conduit and panel capacity for tomorrow’s. We typically recommend installing ports for 5 to 10 percent of spaces at opening, with raceway and panel space roughed in for 20 percent or more. The conduit is cheap during construction and expensive after the slab is poured. Networked chargers with load management let the building add ports later without touching the service, and let the owner bill residents for the electricity they use.

    Placement matters too: cluster the ports near the panel to shorten feeders, keep them out of the lowest point of a garage where water collects, and reserve at least one accessible space with the extra clearance an accessible charging space needs.

    The decision in one sentence

    Residents need chargers that fill a car overnight, not chargers that fill a car at lunch. Level 2, planned with room to grow, is the answer for nearly every apartment building; DC fast charging belongs on the retail side of a mixed-use project or as a single shared amenity on a large campus.

    Sunderland Electric designs and installs EV charging and site power for multifamily, mixed-use and commercial properties across Connecticut. Send us your drawings and we will size the charging plan to the service you have.

  • Retail Fit-Out Electrical in Mixed-Use Buildings: What to Settle Before the Lease Is Signed

    Retail Fit-Out Electrical in Mixed-Use Buildings: What to Settle Before the Lease Is Signed

    The ground floor of a mixed-use building is where the electrical design gets complicated. The apartments above are repetitive and predictable. The retail below is a blank shell that will be leased to a tenant nobody has met yet, who may turn out to be a nail salon, a restaurant with a 200-amp kitchen, or a bank branch with a server room. The decisions a developer makes about that space during base-building construction decide how painful every future lease will be.

    Having built both the base buildings and the fit-outs inside them for brands like Starbucks, Restoration Hardware and Buffalo Wild Wings, here is what we would settle before the shell is finished and before the lease is signed.

    Decide the retail power allowance early, and make it generous

    Base building

    The cheapest time to give a retail bay power is while the switchgear is being ordered. A common mistake is sizing each retail space at the minimum the code requires for a generic mercantile occupancy, then discovering that the only tenant who wants the corner is a restaurant. Restaurants, medical and fitness tenants routinely need two to four times the power of a boutique. Bringing a second feeder to a bay after the ceiling above is finished and the apartments are occupied costs many times what it costs during construction.

    Our rule of thumb for developers: size the retail distribution for the heaviest tenant you would accept at each bay, not the lightest, and put the spare capacity in the gear even if the feeders are run later. Give every bay its own meter, its own disconnect and a conduit pathway back to the electrical room with room to pull more.

    Write the lease around a clear line: landlord’s work vs. tenant’s work

    Most disputes we see on retail fit-outs trace back to a lease exhibit that was vague about where the landlord’s electrical stops. The clean version reads something like this: the landlord delivers a metered service of a stated size, terminated at a disconnect or panel at a stated location inside the premises, with a stated number of empty conduits to the roof and to the electrical room. Everything from that point in is tenant’s work. Any upgrade to the landlord’s service to meet tenant load is tenant’s cost, at landlord’s option through landlord’s contractor.

    Spell out the size in amps and voltage, not in words like “adequate.” Put the location on a drawing. If the tenant’s signage, HVAC or kitchen exhaust will need power on the roof, say who runs it and who maintains it.

    Coordinate the systems that cross the line

    Some systems cannot be split neatly between landlord and tenant, and those need an owner from day one.

    • Fire alarm. The retail space is part of the building’s fire alarm system, so tenant devices have to tie into the base-building panel, be programmed by whoever maintains that panel, and be tested together. Decide whether tenant fire alarm work must go through the landlord’s fire alarm contractor; on most buildings it should.
    • Kitchen hood suppression and exhaust interlocks. A restaurant’s suppression system has to shut down gas and power under the hood and signal the building alarm. That is a three-way coordination between the tenant’s kitchen contractor, the fire alarm contractor and the electrician.
    • Signage and exterior lighting. Storefront signs, canopy lighting and blade signs usually run on the house meter or the tenant meter depending on who controls them. Pick one, and provide the circuit during base building.
    • Emergency and egress lighting. Shared corridors, rear exits and the path through the retail to the street are life-safety items the inspector will test as part of the building, not the tenant.

    Plan the shutdowns, because you will have residents upstairs

    By the time the first retail tenant builds out, the apartments are often occupied. Any work in the main electrical room, any new feeder from the switchgear and any fire alarm programming can affect the people living above. A good fit-out contractor schedules those events, notifies the property manager, and works nights where a shutdown is unavoidable. A lease that requires the tenant’s contractor to coordinate shutdowns through the landlord, with notice, saves everyone a bad week.

    Inspections and the certificate of occupancy

    A retail fit-out gets its own electrical permit and its own inspections, but the certificate of occupancy for the tenant space depends on the base-building systems being in order, especially fire alarm. If the base building has open items, the tenant’s opening date is at risk, and that becomes a landlord problem fast. We recommend closing out the base-building electrical fully, with the fire alarm acceptance test complete, before the first tenant starts work.

    A short checklist for developers

    • Size retail distribution for the heaviest acceptable tenant per bay, with spare capacity in the gear.
    • Separate meter, disconnect and spare conduits for every bay.
    • Lease exhibit states service size, termination point and the landlord/tenant line on a drawing.
    • Tenant fire alarm work routed through the building’s fire alarm contractor.
    • Roof power for signage, HVAC and exhaust provided during base building.
    • Shutdown procedure written into the lease.
    • Base-building electrical and fire alarm closed out before the first tenant mobilizes.

    Sunderland Electric builds the base-building electrical for mixed-use projects across Connecticut and the retail fit-outs that follow, which is why we care about getting the handoff between them right. If you are planning a mixed-use project, send us the drawings and we will flag the retail power questions before they cost anything.

  • Electrical Due Diligence Before Buying an Apartment Building in Connecticut

    Electrical Due Diligence Before Buying an Apartment Building in Connecticut

    Most buyers of an existing apartment building in Connecticut get a roof report, a boiler report and an environmental Phase I. Far fewer get a real look at the electrical system, which is odd, because the electrical is often the single most expensive thing to fix after closing and the hardest to see. A 30-minute walk-through with an electrical contractor who builds this building type can tell you whether you are buying a building with a few deferred-maintenance items or a building that needs a new service.

    Here is what we look at when an owner, investor or property manager asks us to walk a building before they buy it.

    1. The service: is there enough power, and is it the utility’s problem or yours?

    Start at the point where the utility ends and the building begins. We want to know the service size in amps and volts, whether it is overhead or underground, the age and manufacturer of the main switchgear or service equipment, and whether the utility’s transformer is on a pad outside or in a vault inside the building. An interior transformer vault that belongs to the owner is a line item most buyers never budget for.

    Then we compare the service to the loads. A 1970s building that was built with electric baseboard, or that has since added central air, in-unit laundry and a few EV chargers, may be running close to its limit. If the business plan calls for more of any of those, the service, not the units, is where the money goes. A service upgrade in an occupied building means a utility application, a possible shutdown and coordination with every tenant.

    2. Metering: who pays for what, and does the equipment still work?

    Confirm how the building is metered. Individually metered units push the electric bill to tenants and simplify operations; a master-metered building means the owner pays everything and recovers it through rent or a submetering program. The answer changes the underwriting, so verify it with the meter bank, not the offering memorandum. We wrote about the trade-offs in individual vs. master metering for apartment buildings.

    While you are at the meter bank, look at the meter sockets and the disconnects. Old meter stacks from discontinued manufacturers can be impossible to get parts for, and a failed stack can take a whole wing offline until it is replaced.

    3. Distribution: panels, feeders and the manufacturers to flag

    Open a representative sample of unit panels and all of the house panels. We are checking for manufacturer and age, signs of overheating, double-tapped breakers, missing covers and the general quality of past work. Certain older panel brands have known failure histories, and insurers increasingly ask about them. If the building has them, plan to replace them, and get that number into the deal.

    Look at the feeders in the electrical rooms and risers, too. Aluminum branch wiring from the late 1960s and 1970s, cloth-covered wiring, and conduit runs that have been cut and abandoned all tell you how much of the building you will eventually be rewiring.

    4. Fire alarm and emergency lighting: the systems that can stop a sale

    The fire alarm panel tells you a lot in a few minutes: the make and age, whether it is in trouble, the date of the last inspection tag, and whether the devices in the corridors match the panel or have been replaced piecemeal. A fire alarm system that is no longer supported by its manufacturer is a capital item, and the fire marshal can require it to be addressed before a change of use, a major renovation or, in some towns, a change of ownership.

    Emergency lighting and exit signs are cheaper, but they are inspected, and the number of dead units is a reliable proxy for how well the building has been maintained overall. See what inspectors check before the certificate of occupancy for the full list.

    5. Common areas, site and amenities

    Walk the parking lot at dusk if you can. Site lighting that is half dark is a security and liability issue, and pole bases, underground feeds and old HID fixtures are each their own repair. Inside, corridor and stairwell lighting on timers or old fluorescents is usually the easiest early win: an LED retrofit with occupancy controls cuts the house electric bill quickly and is often rebated by the utility.

    If the plan includes EV charging, check what the service and the parking layout can support before promising it to tenants. EV-ready apartment parking explains how load management lets a building add chargers without a service upgrade.

    6. Permits and records

    Pull the electrical permit history from the town building department. Unpermitted work shows up as a gap between what you see in the panels and what the town has on file, and it becomes your problem once you own the building. Ask the seller for panel schedules, as-built drawings, the fire alarm inspection reports and any utility correspondence. If none of that exists, that is a finding in itself.

    What you get out of it

    A proper electrical walk-through produces three things: a short list of items that need attention now, a longer list of capital items with rough costs and a timeframe, and a clear answer to the question that matters most to the business plan: can this service support what you want to do with the building? That is the information that belongs in your capital reserve and your negotiation, not in a surprise six months after closing.

    Sunderland Electric walks existing apartment and mixed-use buildings for owners, investors and property managers across Connecticut, and our commercial service department handles the repairs and upgrades that come out of it. Get in touch if you have a building under contract.

  • How to Prequalify an Electrical Subcontractor for a Multifamily Project

    How to Prequalify an Electrical Subcontractor for a Multifamily Project

    The electrical subcontractor carries one of the largest trade packages on a multifamily project and touches almost every phase of the schedule. Before awarding the work, general contractors and developers should look past the bottom-line number. Here is a practical checklist.

    1. License and insurance

    In Connecticut, verify the contractor’s license with the Department of Consumer Protection. An unlimited electrical contractor license carries the E-1 designation (for example, ELC.0188114-E1). Confirm general liability, workers’ compensation and umbrella coverage meet your contract requirements.

    2. Bonding capacity

    If the project requires payment and performance bonds, confirm the subcontractor can bond the work and still carry its other projects.

    3. Relevant experience

    Ask for comparable buildings: unit count, construction type, mixed-use components. Multifamily work rewards repetition and floor-by-floor production planning, which is different from one-off commercial jobs.

    4. Manpower and supervision

    Who will run the job, and how many licensed electricians can be committed at peak? A strong foreman is often the difference between a project that hits inspections and one that slips.

    5. Safety record

    Request the safety program and experience modification rate (EMR), and ask how the subcontractor coordinates with your site safety plan.

    6. Preconstruction input

    The best electrical subcontractors flag coordination problems and offer value-engineering options during bidding, not after award.

    Prequalifying an electrical contractor for a Connecticut project? See how Sunderland Electric works or request a bid.

  • Electrical Service and Meter Centers for Apartment Buildings: A Planning Guide for Connecticut Developers

    Electrical Service and Meter Centers for Apartment Buildings: A Planning Guide for Connecticut Developers

    In an apartment building, the electrical service and meter centers are the backbone everything else hangs on. Decisions made here early in design affect cost, schedule, utility coordination and how easily the building can grow. Here is what Connecticut developers and general contractors should plan for.

    Size the service for real loads

    Service size is driven by the load calculation: unit count, heating and cooling type, cooking, common areas, elevators, and any EV charging. All-electric buildings with heat pumps and induction ranges carry very different loads from gas-heated buildings, so the mechanical design needs to be settled before the service is. Oversizing wastes money on gear and utility fees; undersizing creates expensive problems later.

    Start the utility process early

    The utility’s design, transformer and metering requirements often set the critical path. Applying early, confirming transformer location and pad requirements, and getting metering approval on the drawings keeps energization from holding up occupancy.

    Lay out meter centers for the building

    • Location: a central electrical room versus distributed meter rooms changes feeder lengths and costs.
    • Mixed-use separation: retail tenants usually need their own metering and space for future fit-outs.
    • Clearances and access: working space, door swings and utility access must be coordinated with the architect early.
    • House loads: common-area lighting, elevators, fire alarm and amenity spaces need their own metered panels.

    Release long-lead gear early

    Switchgear and meter centers can carry long lead times. Getting submittals approved and gear released early protects the schedule.

    Sunderland Electric has built the electrical systems for more than 1,000 apartment units across Connecticut. Send us your drawings and we will review the service design as part of our pricing.